Good day to day, dear YaPovtsy. Long went to to publish the continuation of his immersion in the suburban life finally matured =)
Started building with cabins
Continue walking along the foundation plan. Foundation - monolithic insulated plate with stiffeners. Call this type of foundation and the Swedish stove, oven and Finnish. The essence - warming plate with stiffeners under bearing walls, with a stuffy warm floor and a very even, not to make the screed, and immediately use the surface of the plate as a rough floor. Ie it is glued tile, laminate falls (for underfloor heating).
Built with her husband's sister - two foundation on two adjacent sites.
1. Foundation plan
Forgot to add - please do not break, I finish, I will inform you.
2. The cut - type stiffeners across.
3. Beginning with the markup. Originally sedalali markup is not very correct, after remade. Did callouts, etc. Twine used to understand how the room will be located, so the portions a little on the "Train" with these ropes))
4. Once accepted location, called a tractor and began to dig. Friends who starts, plans to build - and look at the equipment and on the driver. We worked good excavator Volvo, but with shitty gasket between the wheel and the seat, the second was a weak Fiat, but the driver love everything align etc. (He even smiled when he had all neatly gets out of the bucket). The result of the second was better.
5. Remove the fertile layer.
6. At the appointed hour, the car started to come with the sand. The total weight of this machine 45 tons. 15 itself, and 30 tons of sand. Bad they go on zemelku - heavy. The first time I saw that the ground wave goes from the machine as the water from the boat. It felt like clay.
7. Sand. Very good quality. Clean.
8.Fiatik dub, we shed each layer and ramming vibromashinkoy. layers of 7-10 cm.
9. The process is long.
10.
11.
12. sheds must be carefully. From qualitative spilling sand and compacted.
13.
14. Outcome. Sheds and tamp 3 days. Let me remind you - did just two of the foundation.
15. begun to form ribs. How we do it - did the level of sand on an average, after digging up the sand from the ribs and threw on the site. Maybe now is not very clear, then everything will become clear;)
Posted in [mergetime] 1414441943 [/ mergetime]
at the same time began to bury the pipe sewer
16. Slightly ran ahead of the engine))
First, we have marked ribs.
Some pictures made on tel.
17. and then shaped ribs.
18. from another angle.
19. zapilivaem channels) Since we have the exact markings, we easily have marked exits sanitation. Initially adopted the point 0, so the output tubes with height too nebilo.
20. lay the pipe 110 with access to the boiler room, this backup entry into the house. Trailers HDPE pipe for water inlet, water outlet, enter e-wa, wa-e O, well, and so forth.
Posted in [mergetime] 1414442485 [/ mergetime]
2 pipes near - is in the boiler room. As he wrote the backup pipe, and lower, channels for trapika - dog paw wash, because the boiler room separate entrance from under the carport, you can wash when changing tires, etc.
21. The pipe joints are coated with silicone so, just in case wrapped with tape, so that when "perturbation" is not popped tube. Although they would not have jumped, "fear has big eyes»))
22. Always need bias. But do not overdo it - otherwise the water will flow away, and all that firmer, will lie in the pipe))
23. Came receiver for the well
24. Came to the well pipe.
Posted in [mergetime] 1414442805 [/ mergetime]
At the same time, and pipe for drainage sewers.
25. The pipe sawed in size.
26. Came and hatches. in our region, there is nothing normal.
27. At the same time ordered and receivers for vodostochki.
28. Put in place the wells.
29. At the same time decided to just lay around the perimeter drains. as inspection chambers used a red tube 110.
30. A slightly different angle. Wagon came extruded polystyrene. And the Kirov region. not advertising, but there really is cheapest. Quality Pts. good.
31. Another view
32. Over drenazhki laid storm sewers. There is already not use perforated pipe. Drainage wrap up in a layer of gravel and sand from the enclosing geotextile.
33.
34. it's tail for livnevki with canopy
35.
36. shaped ribs and grounds, laid geotextile and gravel layer 100 mm. Gravel also ramming.
37. harboring site and also go to sleep with gravel. All of the project.
Posted in [mergetime] 1414443541 [/ mergetime]
Right at the bottom is visible pattern, which asked the geometry of the ribs.
38. Puts Epps.
Fungi are used for fixing to all at this stage "left»))
40.
41.
41. "Ziggurats" from a different angle))
42. Finish laid insulation. Top, on the ground layer of 200 mm.
43. knit reinforcement.
44. Put the permanent formwork. formwork is glued from Epps and cut sheets of DSP.
Posted in [mergetime] 1414443887 [/ mergetime]
Ah, yes. Was placed to prevent leakage teh.plenka laitance.
45. under the net stretched HDPE pipes for water supply wiring. pipe 32. It is very well include metal-base 16 diameter.
46. The same came metalplast 16th diameter
47. Fasten the formwork
48.
49. use the old commercial equipment in Qual-ve rack under floor heating comb.
50.
51. no advertising. the quality is excellent))
52. Puts the first loop of floor heating. Step pattern designed software method based on windows, doorways, etc.
53. tubes fixed temporarily. because are raised to the second layer of the grid.
54.
55. perform system tests
56.
57. bent such & quot; Frogs & quot ;, for lifting the second layer of the grid.
58. tried out on the terrace. She immediately filled with the base plate.
59. pulled pipe underfloor heating to the upper grid. At any fixed binding wire through soft ring
60. missed the picture from the start mating fittings. Maybe someone will be particularly interested in this moment)
61. pour concrete. 38 cubes.
62. The rainy season has begun, the soil was thin, mixers 8 cubes Chinese with a dead transmission of which at the slightest load hrenachilo oil (((. Take our KAMAZ - they do not care where and how to go
63. use a floating screed Italian - very good thing!
64. leveled, smoothed, check disappears.
65. In principle all. Everything turned out very well. second foundation also filled later. Only hard to take away. total of 92 tons of foundation. on the pillow took 270 tons of sand on every house, about 50 cubic meters of gravel.
Posted in [mergetime] 1414445113 [/ mergetime]
actually safe and designers such stiffeners for my home are not needed. You could do much cheaper and easier. but I do not regret a warm foundation, strong. Make concrete B22, 5
Thanks for watching. If possible, I will answer your questions.
Started building with cabins
Continue walking along the foundation plan. Foundation - monolithic insulated plate with stiffeners. Call this type of foundation and the Swedish stove, oven and Finnish. The essence - warming plate with stiffeners under bearing walls, with a stuffy warm floor and a very even, not to make the screed, and immediately use the surface of the plate as a rough floor. Ie it is glued tile, laminate falls (for underfloor heating).
Built with her husband's sister - two foundation on two adjacent sites.
1. Foundation plan
Forgot to add - please do not break, I finish, I will inform you.
2. The cut - type stiffeners across.
3. Beginning with the markup. Originally sedalali markup is not very correct, after remade. Did callouts, etc. Twine used to understand how the room will be located, so the portions a little on the "Train" with these ropes))
4. Once accepted location, called a tractor and began to dig. Friends who starts, plans to build - and look at the equipment and on the driver. We worked good excavator Volvo, but with shitty gasket between the wheel and the seat, the second was a weak Fiat, but the driver love everything align etc. (He even smiled when he had all neatly gets out of the bucket). The result of the second was better.
5. Remove the fertile layer.
6. At the appointed hour, the car started to come with the sand. The total weight of this machine 45 tons. 15 itself, and 30 tons of sand. Bad they go on zemelku - heavy. The first time I saw that the ground wave goes from the machine as the water from the boat. It felt like clay.
7. Sand. Very good quality. Clean.
8.Fiatik dub, we shed each layer and ramming vibromashinkoy. layers of 7-10 cm.
9. The process is long.
10.
11.
12. sheds must be carefully. From qualitative spilling sand and compacted.
13.
14. Outcome. Sheds and tamp 3 days. Let me remind you - did just two of the foundation.
15. begun to form ribs. How we do it - did the level of sand on an average, after digging up the sand from the ribs and threw on the site. Maybe now is not very clear, then everything will become clear;)
Posted in [mergetime] 1414441943 [/ mergetime]
at the same time began to bury the pipe sewer
16. Slightly ran ahead of the engine))
First, we have marked ribs.
Some pictures made on tel.
17. and then shaped ribs.
18. from another angle.
19. zapilivaem channels) Since we have the exact markings, we easily have marked exits sanitation. Initially adopted the point 0, so the output tubes with height too nebilo.
20. lay the pipe 110 with access to the boiler room, this backup entry into the house. Trailers HDPE pipe for water inlet, water outlet, enter e-wa, wa-e O, well, and so forth.
Posted in [mergetime] 1414442485 [/ mergetime]
2 pipes near - is in the boiler room. As he wrote the backup pipe, and lower, channels for trapika - dog paw wash, because the boiler room separate entrance from under the carport, you can wash when changing tires, etc.
21. The pipe joints are coated with silicone so, just in case wrapped with tape, so that when "perturbation" is not popped tube. Although they would not have jumped, "fear has big eyes»))
22. Always need bias. But do not overdo it - otherwise the water will flow away, and all that firmer, will lie in the pipe))
23. Came receiver for the well
24. Came to the well pipe.
Posted in [mergetime] 1414442805 [/ mergetime]
At the same time, and pipe for drainage sewers.
25. The pipe sawed in size.
26. Came and hatches. in our region, there is nothing normal.
27. At the same time ordered and receivers for vodostochki.
28. Put in place the wells.
29. At the same time decided to just lay around the perimeter drains. as inspection chambers used a red tube 110.
30. A slightly different angle. Wagon came extruded polystyrene. And the Kirov region. not advertising, but there really is cheapest. Quality Pts. good.
31. Another view
32. Over drenazhki laid storm sewers. There is already not use perforated pipe. Drainage wrap up in a layer of gravel and sand from the enclosing geotextile.
33.
34. it's tail for livnevki with canopy
35.
36. shaped ribs and grounds, laid geotextile and gravel layer 100 mm. Gravel also ramming.
37. harboring site and also go to sleep with gravel. All of the project.
Posted in [mergetime] 1414443541 [/ mergetime]
Right at the bottom is visible pattern, which asked the geometry of the ribs.
38. Puts Epps.
Fungi are used for fixing to all at this stage "left»))
40.
41.
41. "Ziggurats" from a different angle))
42. Finish laid insulation. Top, on the ground layer of 200 mm.
43. knit reinforcement.
44. Put the permanent formwork. formwork is glued from Epps and cut sheets of DSP.
Posted in [mergetime] 1414443887 [/ mergetime]
Ah, yes. Was placed to prevent leakage teh.plenka laitance.
45. under the net stretched HDPE pipes for water supply wiring. pipe 32. It is very well include metal-base 16 diameter.
46. The same came metalplast 16th diameter
47. Fasten the formwork
48.
49. use the old commercial equipment in Qual-ve rack under floor heating comb.
50.
51. no advertising. the quality is excellent))
52. Puts the first loop of floor heating. Step pattern designed software method based on windows, doorways, etc.
53. tubes fixed temporarily. because are raised to the second layer of the grid.
54.
55. perform system tests
56.
57. bent such & quot; Frogs & quot ;, for lifting the second layer of the grid.
58. tried out on the terrace. She immediately filled with the base plate.
59. pulled pipe underfloor heating to the upper grid. At any fixed binding wire through soft ring
60. missed the picture from the start mating fittings. Maybe someone will be particularly interested in this moment)
61. pour concrete. 38 cubes.
62. The rainy season has begun, the soil was thin, mixers 8 cubes Chinese with a dead transmission of which at the slightest load hrenachilo oil (((. Take our KAMAZ - they do not care where and how to go
63. use a floating screed Italian - very good thing!
64. leveled, smoothed, check disappears.
65. In principle all. Everything turned out very well. second foundation also filled later. Only hard to take away. total of 92 tons of foundation. on the pillow took 270 tons of sand on every house, about 50 cubic meters of gravel.
Posted in [mergetime] 1414445113 [/ mergetime]
actually safe and designers such stiffeners for my home are not needed. You could do much cheaper and easier. but I do not regret a warm foundation, strong. Make concrete B22, 5
Thanks for watching. If possible, I will answer your questions.