Gas boiler.

Introducing gas into the boiler. On a branch electromagnetic filter counter. Pressure 2kPa. SHRP street.

25 images + text.





We have three boilers, two workers one in reserve. Which in reserve, analyze it.



With the main branch, the gas is fed boilers. Before burner various sensors, the signal from which is converted to digital and applied to the shield.



Piezometric tube.



Himself shield currently disabled. All readings are displayed on it.



The so-called "combustion managerĀ»



Automatic boilers for German. Boilers OUR!



Pskov.



Options.



A little labor, take out the burner. Look conductive!



They took out his heart.



That itself burner, the boiler was basic. As a result of her work on the burner itself forms plaque in the kettle. Removed mechanically.



It has a pilot light and a reference electrode. In these areas especially carefully. Clean.



Electrodes, too, the same as the candles in the machines.



On the burner defect is found, where it is necessary to inform, and write. (Just in case)



Set back. The burner is fixed by a single bolt. Connect all the tubes, sensors.



Protective cover, burner as German automation.



Start on the first try failed, burst hose, which monitors the pressure in the furnace. Parse again. Is located. Me. So-called "peepersĀ»



The main work is done. More ... can someone interesno.Teplonositel heated, a bunch of parameters are controlled sensors.



All there makeup ...



The heat exchanger, there are two. One was held in reserve, but over time the power was not enough, in parallel, some time has passed and the 2 missing.



Both of the pair.



Himpodgotovka.



Network pumps, one primary, one reserve, and the third when he wants.



and the whole thing to the consumer. Everything!