The author decided to build a country house, which at first was planned as a summer cottage accommodation and temporary winter arrivals. Mostly built, he and his father, without the use of cheap labor of non-Slavic appearance. Under the cut you will see the whole process of the construction of this extraordinary adventure lodge, which was built to remind the whole two weeks.
Vacation home



Well, let's start: the foundation pile, poured on top of "coppers."
Day One:

Vacation home

Ready rail, begin to lay a temporary overlap. End of Day - time to put together and put the first wall.

Vacation home

Day Two:
Collect and raise the walls, everything is quite simple and easy, there are drawings (he produced) by him cut into planks and lying to cobble together a wall, then set, securing the struts time

Vacation home

This is the result of the second day

Vacation home

Day Three:
The ends do with gables, for savvy - system "balun". To be able to move "upstairs" is going to shut off and throws a few planks.

Vacation home

Rafters on the second front had not had time to put - do not have the strength.

At the end of the day:

Vacation home

Fourth:
We put the rafters over the entire length, as you can see the weather began to deteriorate, and if the first three days I was working in a T-shirt, all posledeyuschie did not get out of hoodies - August in Petrograd unpredictable.

Vacation home

End of Day:
Already I want only one thing: to fall and fall asleep :)

Vacation home

Fifth:
Taut membrane began to close the roof Ondulin, according to the law of meanness rose to a gale, and the house is not carried away - had to quickly sew up the gable wall and part of the second part of the roof OSB and do not close.

Vacation home

End of Day:

Vacation home

Sixth:
Closed roof, sewn two walls down force even at the photograph no longer exists. The house is covered - you can breathe a little, go to town to wash, to buy food and just lie :)

Vacation home

End of Day:

Vacation home

One day of rest, rebounded slightly, and again in the battle.
Day Seven:

Vacation home

Insulated, top closure membrane until the stapler, then all the racks stuffed bars. Of course it started to rain ...

Vacation home

End of the day: Are the two walls.

Vacation home

Eighth:

Vacation home

The third and fourth walls are ready.

Vacation home

Ninth:

Vacation home

They brought and placed windows, this time I sewed four hours one wall siding. While he is taking a job as altered until dopenivali - the time has gone, at the end of the day it succeeded:

Vacation home

Tenth:

Vacation home

Sewed the two gable farther - the faster it turns out to work, the last blank wall sewed all for a cheap Chinese polchasa.Votknul door. Here's the view from the other side:

Vacation home

Eleventh:

Digging a grave for septic

Vacation home

Customer submerged, buried in the same supply pipe to the desired slope

Vacation home

Twelfth:

Vacation home

Insulate and bury

Vacation home

Vacation home

All the house is closed, buried septic tank, the season is over.