How are stadiums 2018 World Cup football now

Kazan
Capacity: 45,000
Cost: 14 billion rubles
Plan date: August 2014
The stadium, which was built for the Universiade-2013, is still waiting for the first official match. Lawn a bed last fall, but he fell ill and was eliminated. A second attempt to do right now. The debut of the arena in the Premier League is scheduled for August 17, when the "Rubin" will "Locomotive". The club will play here until the summer of 2015, when the arena will convert into a pool for the World Cup in water sports. Kazan Stadium - universal. In May, it was the last call, and in June iftar (evening meal during the holy month of Ramadan) for 3,000 Muslims, during which it was cooked pilaf about a ton.
Now:





Moscow «Spartak»
Capacity: 42,000 (in the 2014 World Cup - 44 thousand)
Cost: 15 billion rubles
Plan date: September 2014
Opening Spartakovskaya arena 5 September a friendly match with the "Red Star". The club is already selling tickets for the season. The first official game - in the 7th round with the "Torpedo" after six games on the road. Also open on September 5 and the metro station "Spartacus." Director-General appointed Alexander Atamanenko Stadium - the former general director of "Donbass-Arena».
Right now:



What should have



Sochi
Capacity: 40,000
Cost: 15 billion rubles
Plan date: second half of 2016
Sochi "Fischt" worked for the Olympics and waiting for reconstruction, during which dismantled the central part of the roof. Work is expected to finish by the end of 2016, to host the matches of the Confederations Cup. The local mayor's office are going to open the stadium for tours and dream to the end of reconstruction in the city there was a Premier League team.
Right now:



What should have



St. Petersburg
Capacity: 69,000
Cost: 35 billion rubles
Plan date: June 2016
Time of Troubles arena on Krestovsky should stay behind. Officials said that the time and cost no more change. By the fall of the first promise to establish elements of the facade of the stadium.
Member of the Legislative Assembly of St. Petersburg, Vitaly Milon suggested naming a stadium under construction on Krestovsky "Putin arena." Convinced Milonova if the stadium will be named after the president, it will be a "monument of the era, which is now facing the country, a symbol embodied the zeitgeist of modern Russia».
Right now:



What should have



Nizhny Novgorod
Capacity: 45,000 at the 2018 World Cup, after 35
Cost: 15 billion rubles
Plan completion: end of 2016
In Nizhny Novgorod, the year 2014 - the year of clearing the area for construction of the new stadium. It began in February and continues until now. Promise to begin construction later this year. On account of Nizhny Novgorod two records. Negative: The Chamber of Accounts revealed overvaluation of the stadium 208 million rubles. This is more than in other cities. Positive: The bottom of the first Russian cities presented the concept of territory planning for the 2018 World Cup.
Right now



What should have



Moscow, «Luzhniki»
Capacity: 81,000
Price: 19, 7 billion rubles
Plan for Completion: May 2017
In the main stadium of the country a large-scale reconstruction. Podtribunnye dismantle the stands and premises. Stadium after the upgrade will be a purely football, will seat 81,000 spectators and get a natural lawn. The chief architect of Moscow has promised that there will finally comfortable to watch football.
Sports Minister Vitaly Mutko: "We have no right in 2018 in" Luzhniki "in the presence of 80 thousand fans to take and give some out there to Algeria or conditional Jamaica»
Right now



What should have



Ekaterinburg
Capacity: 47,000 at the 2018 World Cup, after 33
Cost: 15 billion rubles
Plan date: 2017
In Yekaterinburg remodel just two stadium for the 2018 World Cup. "Central" - games and "Uralmash" - for training teams. While the "Ural" will play their home matches in Nizhny Tagil, builders will give way to the new stadium of the club "Ural gems».
Mayor of Yekaterinburg Yevgeny Roizman, in December last year, was indignant: "To reconstruct the reconstructed stadium, spend it 12-15 billion - a stupid, inept and, dare I say it, a crime»
In March this year yet accepted it: "Reconstruction - painful and sad, but what to do? We will endure. My task, that nothing broke »
Right now



What should have



Samara
Capacity: 45,000
Cost: 13 billion rubles
Plan date: 2017
Samara originally going to build an arena in the direction of the rivers Volga and Samara, but because of the high cost of the plan refused and moved the building in working-class district of the city. July 21 there will be laid stone. This event could have happened before, but the mayor's office did not give the developer a building permit because of problems with documents.
In April, local MPs propose to name Samara Stadium "Crimea", "to emphasize our patriotic attitude to the Crimean events».
Right now



What should have



Kaliningrad
Capacity: 45,000 at the 2018 World Cup, after 30
Cost: 15 billion rubles
Plan date: 2017
In Kaliningrad, a major problem in the construction of the stadium in 2018 became a marshy soil, which had liberally showered with sand. She decided with the help of 1 billion rubles. Further it should be easier. According to the designer, the stadium is quite simple for the main building, as it contains no architectural excesses.
Vitaly Mutko: "This is the center of Kaliningrad, it is 10 meters from the tomb of Kant, and we will be sure to construct, despite all the difficulties»
Right now



What should have



Saransk
Capacity: 45,000 at the 2018 World Cup, after 30
Price: 13, 5 billion rubles
Plan date: 2017
The construction of the arena in Saransk had to stop for the adjustment of the project due to the fact that the capital of Mordovia will need to take not only the matches of the group stage World Cup, but the playoffs. Earlier this year, the head of state reported that the stadium is ready for 15%, and the resumption of construction will happen this summer.
Right now



What should have



Rostov-on-Don
Capacity: 45,000 at the 2018 World Cup, after 35
Price: 14, 5 billion rubles
Plan date: 2017
This year - for the start of construction of many stadiums 2018. The construction of the arena on the left bank of the Don was to begin in June, but will start in early autumn. Now project documentation is on the adjustment.
Right now



What should have



Volgograd
Capacity: 45,000 at the 2018 World Cup, after 35
Price: 14, 5 billion rubles
Plan date: 2017-2018
Volgograd - city is the most laggard 2018. In early July, the stadium project has not passed the state examination, the designers have received about 40 comments. A second attempt was made a few days ago. If it will be more successful in August will begin to demolish the old stadium, and in November, probably will start new construction. A bit of "Rotor". In May, the club played the last match at the stadium "Central" with sorrow voluntarily dropped in the second league.
Right now



What should have



Source: sporter.md