Viluiskaya HPP





HPP construction began in 1960, ended in 1978. The power plant was built in the 2nd stage, called HPS-I and HPP-II.

Composition hydroelectric facilities: dam 600 m long and 75 m maximum height

Power HPP - 680 MW,.
The building HPP-I has 4 Kaplan hydro capacity of 85 MW
The building HES-II has 4 Francis hydro capacity of 85 MW.

From the station, laid 5 220 kV transmission lines in the Lena through peaceful, and with a successful Aikhal.

Viluiskaya HPP gave the opportunity to start a large-scale development of diamond deposits in Yakutia. The main consumer of electricity is JSC "ALROSA". Cost of 1 kWh of electricity in 2013 - 90 kopecks.

Viluiskaya HPP was built in extremely difficult conditions of permafrost. Many designs were worked out for the first time.

29 photos will be

Viluiskaya HPP



The beginning of construction in 1960

Viluiskaya HPP

Laying the foundation of loam in the dam - everything happens at subzero temperatures

Viluiskaya HPP

Construction of the first stage of HPP-1

Viluiskaya HPP

Again blow the dam - is seen as the ground is heated with a heat gun, and then ukatyvayut laden dump trucks. By stacking technology made in the winter and now round the dam has an internal temperature of minus 5, 5. In fact - the dam huge chunk of frozen clay

Viluiskaya HPP

What used to be a beautiful girl!

Viluiskaya HPP

Volute hydroelectric

Viluiskaya HPP

Pouring concrete using Zielke - there was no cement

Viluiskaya HPP

Start of construction of the receiving water

Viluiskaya HPP

There soon will flood all

Viluiskaya HPP

Flooding water intake HPP-1

Viluiskaya HPP

Delivery transformer

Viluiskaya HPP

Modern look

Viluiskaya HPP

GES-1 hydroelectric generator

Viluiskaya HPP

Computer room HPP-2

Viluiskaya HPP

Incision along the axis of hydroelectric stations: Water from the upper pool that the water enters the volute and results in rotation of the impeller wheel in turn rigidly attached to the rotor during rotation which is produced electricity

Viluiskaya HPP

And here is the very turbine wheel

Viluiskaya HPP

And this is the stator within which the rotor is spinning

Viluiskaya HPP

And here is the rotor that rotates inside the stator 187 with a speed 5 rpm and the gap between the stator and the rotor is not more than 20 mm and not less than 5 mm

Viluiskaya HPP

Panel automation - as postroili- way it works

Viluiskaya HPP

Modern turbine speed control - it is responsible for the frequency of 50 Hz. This control is managed using a free system Windows CE

Viluiskaya HPP

Busbar from hydro - rated current of 4200 amps for short circuit over 20,000 Amps

Viluiskaya HPP

Busway runs from the stator through the switch to the transformer, where the generator voltage is increased to 13,800 volts 220,000 volts.

Viluiskaya HPP

With all of the transformer on the wire enters the ISG-220 (indoor switchgear voltage 220,000 volts) which establishes such air switches CDH-220 (they are controlled by air to 20 atmospheres)

Viluiskaya HPP

Phone for direct connection to the main control board (main control room)

Viluiskaya HPP

The main control panel from the time of construction in 1965 has never changed

Viluiskaya HPP

The most important instrument in the MCR - frequency. Ideally, there should always be 50 Hz.

Viluiskaya HPP

I almost forgot to mash.zale HPP-2 grow tangerines and it's not photoshop.

Viluiskaya HPP

Night photo of the dam - this is the last PHOTO - can kick

Viluiskaya HPP

Source: ">