Mad accident at the nuclear power plant near St. Petersburg

On units under construction of Leningrad NPP-2 collapsed. A similar state of emergency in the construction history of domestic atomstroya did not know ...

source

A small digression. Actually, why I am personally concerned about this issue. The first nuclear power plant in Belarus will build just this Russian company for this technology.

The catastrophic consequences of

According to the source, at the time close to the leadership "of St. Petersburg AEP" cause of accident was bungling and incompetence. We were violated design and construction technology. Back in late May, the builders discovered deviation reinforcement embedded in the outer protective shell of the block. At around 22 meters, it was 600 mm from the vertical. Reasons establish the commission, but experts Sosnovy Bor branch of AEP believes that the state of emergency had happened due to the lack of rigid reinforcement in the project, which would have fixed the valve.

The builders took up the elimination of the detected defect, they were able to straighten rebar, reaching a height of 12 meters. The remaining ten-meter strip of metal was not recorded and available to "walk" in the wind. That is why the July 17 collapsed. Only by chance, there were no casualties - a few minutes before the collapse of the builders left the jobs went to dinner.





Himself controller

"Information about what is really going on in the construction of Leningrad NPP-2, residents of Sosnovy Bor is practically unknown, - says Oleg Bodrov - a physicist, ecologist, director of the environmental organization" Green World ", a resident of Sosnovy Bor. - Up to the head of the Information Center of Leningrad NPP Averyanov I could not even call on his mobile phone. But we know how to organize the construction ».

According Bodrov, damage is caused by the fact that the construction of Leningrad NPP-2 run out of town, seconded from other regions of Russia. There are guest workers from Ukraine and, possibly, from Belarus. They live outside the Sosnovy Bor, and carry on the work. So, in the village of Black Lahti lives of several hundred workers. They work 12 hours a day, when applying for a job they confiscate passports and in fact they are treated like slaves. Barracks, where they live, are not adapted to life in the winter, there is no hot water, but the workers live there year-round.

"Count on the fact that people working in slave-like conditions, may do good work, it is impossible - says Bodrov. - In addition, during the Soviet era in the construction of Leningrad NPP him the following set of regulatory organizations. Now, the organization design - "Lenatomenergoproekt" - is both a developer and controller ».

Now, to see the result of an accident resulting in a ruff of wire mesh, it is not necessary to go to the territory of the construction site of Leningrad NPP-2 - it can be seen from behind the fence. Experts say that such a state of emergency in the construction of the atomic unit of domestic atomstroya history knows such lyapami wall nuclear units of NPP is not yet constructed.

There is nothing surprising in the fact that the deprivation of basic human working and living conditions migrant workers shalturili not. Another question - why strategic facility erected nonprofessional workers.

Any nuclear facility and its system of physical protection of state secrets. Degree - "secret". Accordingly, work on the construction of Leningrad NPP-2 even loader must have a certain tolerance. It becomes sensitive sites when launching the reactor and at the design stage. First developed physical protection system (PPS), and then to the very "filling". And build any nuclear power plants in the same order: first all cover and put under guard, and only then dig pit. A PPS includes not only the number of security guards, their weapons and change the schedule of posts, but also things such as access roads, the number and layout of the PPC, ditches, fences, concrete perimeter wall, etc. And it is a state secret, to which there is hardly any tolerance of the Belarusian and Ukrainian workers.

Unfortunately, "Rosatom" as a closed organization that her (and its subsidiaries) is practically impossible control. The police and the FMS could theoretically verify the right to work in Russia from migrant workers. But employees of these services on the territory of Leningrad NPP will not start - modal facility.

FSB can verify compliance with the existing PPS standards and compliance with the order of protection of the object. As for the skills and other qualities of workers, materials, technical documentation, the possibility of direct theft or sloppiness in the construction or operation of a nuclear power plant - is unclear why the powers are severely limited. Although control of the security services of nuclear facilities would just be quite understandable. Ideally, of course, together with the public scrutiny.

"Rosatom" - state-owned corporation, on economic issues, and self-controlled unless its own services. Now, if the territory of the Leningrad NPP, God forbid, a terrorist attack will be planned, whereas the FSB can operate. And if, for example, a wall collapse has put into operation the power unit, the prosecutor's office will deal. Which, by the way, works with the applications of citizens, rather than to monitor the situation on a construction site online.

It turns out that "Rosatom" he develops the project, chooses the prime contractor, he pays for the work itself controls, he is mistaken. Answer, I suppose, too, will himself. Only here if something happens to the nuclear power plant is already working, whether an expert to find the defendants?



Source:

Tags

See also

New and interesting