What ships of the Russian Navy will receive in 2014?

So the Navy in 2014, Russia is planning to take part in its 40 combat surface ships and submarines, and support vessels of various classes, said on Friday, ITAR-TASS news agency, Deputy Chief of the Navy armament Rear Admiral Victor Borsuk.

According to last year's forecast of the Navy also planned to accommodate about 40 ships, but many were late with the delivery, and in the end it took about 30.

Taking the calculation OPOZDUNOV last year, analyzed data on schedules major shipyards combat and auxiliary vessels, and of course, prosherstit Vicki made photo review of the warships, which we are promised in 2014.

Just say - in the delivery of many poorly believe, and yet - Photos from done. Judge for yourself. Will be 40 photos.

Battle Fleet:

1. A nuclear missile submarine "Vladimir Monomakh" Project 955 class "Northwind." Displacement 24,000 tons. Pass state tests.





2. multipurpose nuclear submarine of the fourth generation "Severodvinsk" class Project 885 "Ash". Displacement 13,800 tons. Passes test. Take should be later this year.



3. SSK "Novorossiysk". Displacement 3950 tons. According to the plan adopted in June.



4. SSK "Rostov-on-Don." Displacement 3950 tons. Launching in May. According to the plan (according to Wiki) adoption in 2014. Although it is doubtful.



5. SSK "Stary Oskol" Displacement 3950 tons. According to the plan (according to Wiki) adoption in November. Although it is doubtful.



6. The amphibious assault ship "Vladivostok". Displacement 32,000 tons. The plan adopted on November 1.



7. Watchdog frigate "Admiral Kasatonov." Displacement 4,500 tons. According to the plan (according to Wiki) The adoption in 2014. Though doubtful, judging by the difficulty of finding fresh photos.



8. Watchdog frigate "Admiral Essen." Displacement 4,500 tons. According to the plan (according to Wiki) The adoption in 2014. Judging by the photos from August 27. '13 - Again doubtful.



9. Watchdog frigate "Admiral Makarov". Displacement 4,500 tons. According to the plan (according to Wiki) The adoption in 2014. But see for yourself.



10. Frigate "Admiral Gorshkov". Displacement 4,500 tons. Originally we planned to hand over the fleet in 2010. Passes test. Will ZHI at the beginning of 2014, immediately after the installation AU A-192. Accordingly, the plan to take in 2014.



11. Frigate "Admiral Grigorovich". Displacement 4050 tons. It located in a high degree of readiness. Descent is planned in February 2014 with the delivery late in the year. According to the plan (according to Wiki) The adoption in 2014.



12. Corvette "resistant." Displacement 2,200 tonnes. January 15, 2014 came out in the Gulf of Finland on sea trials. Adopt were still 2013, forward to in 2014.



13. Corvette "Perfect." Displacement 2,200 tonnes. According to the plan (according to Wiki) The adoption in 2014. Although it is doubtful. Defense Ministry has postponed for a year corvette sea trials "Perfect", which is being built since 2006 at the Amur shipyard in Komsomolsk-on-Amur. Now tests are planned for 2014 and not for 2013. The reason was the failure of the timing of manufacturing ship.



14. Small rocket ship "Svijazhsk." Tonnage of 950 tons. The tests took place, but the Navy has not yet been adopted. Prepares for lifting the flag.



15. Small rocket ship "Great Ustyug." Tonnage of 950 tons. Formed body. It is completed. Work has begun on the formation of the crew, which is to be formed to 01/02/2014. It must have been taken in 2013. Did not have time. Now, in 2014.



16. Small rocket ship "Uglich". Tonnage of 950 tons. He passed state tests. It must have been taken in 2013. Did not have time. Now, in 2014.



17. countersabotage boat "Rook" (the number is not found). Tonnage of 140 tons. According to the plan adopted in the first half of 2014.



18. Large intelligence ship "Yuri Ivanov." Displacement 2,500 tons. The plan is the adoption by the end of the year.



19. A landing craft air-cavity Project 21820 "Denis Davydov." Tonnage of 280 tons. Opozdun 2013 th. It seems like overwinters in the port. We are waiting for adoption.



20. A landing craft air-cavity "Lieutenant Rimsky-Korsakov." Tonnage of 280 tons. Under construction. According to the plan adopted in 2014.



21. A landing craft air-cavity "Ensign Lermontov." Tonnage of 280 tons. Under construction. According to the plan adopted in 2014.



22, 23, 24, 25 patrol boats "Raptor" head. №701, 702, 703, 704. Displacement of 23 tons each. Build a "Pella". They usually keep the schedule. They plan to take all four in 2014.



26, 27. The two patrol boat project 12150 "Mongoose". The displacement of 30 tons. Will be taken in 2014.



Auxiliary fleet:

1. logistic support vessel "Elbrus". Displacement 9,000 tons. The plan adopted on 25 November. Although fresh pictures found.



2. Maritime transport weapons "Academician Kovalev." Displacement 6300 tons. According to the plan adopted in November.



3. Maritime transport weapons "Academician Alexander." Displacement 6300 tons. According to the plan (according to Wiki) The adoption in 2014. Although it is doubtful.



4. The rescue ship "Igor Belousov." The displacement of 5000 tons. We should take in November.



5. Ship comprehensive port security "Umba". Displacement 2290 tons. Opozdun 2013. Propulsion completed. We are waiting for adoption.



6. Ship comprehensive port security "Print". Displacement 2290 tons. Opozdun 2013. We are waiting for adoption.